New build snagging, what you can demand and when
How the two-year defects period and ten-year warranty really work, and how to get a proper snagging inspection done before you complete, not after.

What snagging actually is
Snagging is the list of faults, unfinished jobs and shoddy workmanship in a new home. Think paint splashes, a sticking door, a cracked tile, sealant that stops halfway, a socket that doesn't work. Most are small. Some aren't.
Here's the thing a lot of first time buyers miss. Every new build has snags. Nobody builds a house without leaving something behind. The question is whether you find them before you hand over the money, or after, when you're chasing a developer who already has your cash.
So treat snagging as a normal part of buying, not as a sign you've picked a rubbish builder.
The two-year defects period
Most developers offer a customer care period, often called a defects period, and for many it runs for the first two years after legal completion. During that time you report faults and the builder comes back to fix them. That's the theory, anyway.
Two things to know. First, the exact length and terms come from your developer's own policy and your warranty paperwork, so read them rather than assuming. Second, the defects period is not a free pass to leave everything until later. Anything you spot before completion is far easier to get fixed, because you still hold the leverage.
Keep every report in writing. Email the customer care team, include photos, date everything and keep a simple log. Phone calls vanish. Emails don't.
The ten-year warranty, and what it won't do
New builds normally come with a ten-year structural warranty from providers such as NHBC, LABC or Premier Guarantee. Your solicitor should check one is in place before you exchange, and your mortgage lender will almost certainly insist on it.
The common set-up is that the builder is responsible for defects in the early years, and the warranty provider's cover for structural problems carries on beyond that. It is mainly about serious structural issues, not about a scuffed skirting board or a dodgy paint finish. Don't expect it to pay for cosmetic snags, and don't expect it to replace a builder who simply won't return your calls.
The exact cover, exclusions and claims process differ by provider and policy. Get the warranty documents, read the summary and ask your solicitor to explain anything vague. If you're relying on particular rights, confirm them with a solicitor, because consumer and warranty rules can change.
Why you inspect before completion, not after
Before completion, the developer wants your money. After completion, the developer wants a new site to finish. You can probably see where the leverage sits.
A pre-completion inspection lets you put faults on a list and ask for them to be fixed before you move in. It also gives you a chance to refuse to complete if the home isn't properly finished, though that's a serious step, so speak to your solicitor first. Walking away or delaying can have consequences under your contract.
Most developers allow a viewing before legal completion, often called a home demonstration or final inspection. Ask for it early. Ask how long you'll get. Then book your own snagger if you want one, and don't let anyone rush you through in twenty minutes with a coffee in your hand.
How to run a snagging inspection
You can hire a professional snagging company, and for a bigger or more complicated home it's often money well spent. They know what to look for and they write a clear report. You can also do a first pass yourself. Either way, go in daylight, and ideally on a dry day so you can spot leaks and damp.
1. Take a torch, a phone for photos, masking tape, a pencil and a plug-in socket tester.
2. Go room by room, top to bottom. Check walls, ceilings, floors, paintwork, windows, doors and fittings.
3. Open and close every window and door. Check locks, handles and seals.
4. Run every tap, flush every loo and check for leaks under sinks and around the bath.
5. Test every socket, light, switch, extractor fan and the heating. Check the boiler has been commissioned.
6. Look outside. Check drainage, fencing, paths, roof lines, render and brickwork.
7. Photograph each fault, label it with tape, then log it in a list with the room and a short description.
Send the list to the developer in writing, ask for a date to fix each item and keep a copy.
What you can reasonably demand
You can reasonably ask for the home to be finished to a proper standard, in line with your contract, the specification and the plans. Safety issues, leaks, non-working systems and incomplete work should be at the top of your list. Cosmetic marks matter too, but be sensible about the order.
If something major is wrong before completion, say so clearly to your solicitor straight away. They can advise whether to delay, ask for a retention, or get a written commitment to fix. Don't make that call alone.
After you move in, keep reporting problems in writing and chase politely, then firmly. If the developer stalls on something that looks serious, check your warranty, speak to your solicitor, and look at whether the developer belongs to a recognised code or redress scheme. Rules in this area can change, so confirm your current rights rather than relying on a guide, this one included.
Common questions
- Can I refuse to complete if there are snags?
- Possibly, if the home isn't properly finished, but it's risky and depends on your contract. Delaying can have consequences, so talk to your solicitor before you decide.
- How long is the defects period on a new build?
- Many developers offer around two years, but the length and terms come from the developer and warranty paperwork. Read yours and ask your solicitor if anything is unclear.
- Does the ten-year warranty cover snagging?
- Not usually. It is mainly aimed at serious structural problems, not cosmetic snags or minor finishing. Early defects are normally the builder's responsibility, so report them in writing.
- Do I need to hire a professional snagger?
- No, but it often helps. A professional knows what to look for and writes a clear report. If you go solo, use a checklist, take photos and send the list to the developer in writing.
Have a property in mind? Check it before you offer.
Paste the Rightmove or Zoopla link and Flatscope reads the lease, the real running costs and the sold-price record, every figure cited. Three free reports a month, no card. Your first run needs no signup.
No listing to hand? See a real sample report firstFrom the buyer's guides
More insights
Flatscope is informational software, not regulated financial or legal advice. Figures are read from public records at the time of writing and can change. Confirm anything decision-critical with your solicitor or surveyor.